MS Project: A Business Partner for Exelis


Ray,

As you requested, I have researched MS Project in regards to its possible use at Exelis.   MS Project is a project management software with many uses and capabilities which would be beneficial to any project management team.  With MS Project, one is able to manage project schedules and finances, communicate and present project information/ status and organize resources to ensure deadlines and commitments are met.  MS Project enables simplified project management by providing tools and resources which will facilitate project planning, resource allocation, financial management as well as collaboration among project teams. 

Given our organizational structure, Exelis should invest in the MS Project software for our Program Management center of excellence as well as our XLSS center of excellence.  Both teams are focused on managing multiple projects simultaneously and would greatly benefit from this software.   MS Project would allow our program managers to efficiently manage their resources and budgets across their span of control.  Our Program Management and XLSS teams currently use MS Excel, PowerPoint and Visio for all project planning needs but are limited to their knowledge with these programs in order to provide useful summaries for our leadership teams as well as for effective project management.   These programs are not designed to aide in project management whereas MS Project is designed to provide a project manager full access to the project design, status, resources and related tasks. 

I would consider an initial investment in 60 MS Project Standard licenses at $589.99 for a total investment of $35,399.40.  I would recommend we provide licenses to each of our four business areas proportionately to their program management (PM) headcount.  For instance, our XYZ Business Area should receive ½ of the licenses that we procure as they have the largest PM Team.  Their portfolio is much more diverse and as a result they have more Program Managers.  While the PMs are responsible for multiple programs, they can use their license to manage all their programs.  MS Project would facilitate the program management process as it would provide PMs with the tools necessary to effectively and efficiently manage their resources, timeline and budget related to their multiple programs.  Additionally, I would recommend an investment in 10 MS Project Standard for our XLSS team to facilitate Six Sigma project design and implementation.  MS Project would be a great tool for our XLSS team as they are constantly working on multiple Green Belt projects at one time and would be able to use MS Project to plan and implement these projects simultaneously.  Investing in 10 licenses for our XLSS team would remove a vast majority of the administrative effort from our XLSS Black Belts and Mentors which could in turn focus on more Green Belt projects to generate additional cost savings for Exelis.   

Ray, as you can see, I am recommending an overall investment of $41,299.30 in MS Project for our Program Management and XLSS teams.  This investment would be an added value for both teams as it would enable effective and efficient project/ program management to coordinate resources and budget wisely from start to finish.  With MS Project, starting a project is as easy as entering tasks and assigning the related duration and start and finish times.  You can include as little or as much detail as needed for each task.  As you enter this data, a Gantt chart is generated.  MS Project will also allow our Program Managers to allocate their resources appropriately to ensure the right team members are assigned to the program.  It even allows you to enter the cost associated to each team member to be able to track budget.  MS Project would also allow Program Managers to share all program related details with the team via PDF reports.  Overall, the investment for Exelis would be minimal compared to the benefits that would be gained through the implementation of MS Project.  The cost can easily be absorbed with the implementation of two Green Belt projects which average about $20k per project. 

Thank you for your time and consideration.  Please advise if you have any additional questions, I would be glad to further discuss with you at your convenience.

 Jackie